Saturday 10 November 2018

We've got a Slab!

We hired an independent inspector for every stages.  The first inspection was the Pre-pour inspection.  It was performed by Darbecca on Monday Nov 5.  Some issues were reported and sent to our site supervisor. All issues were minor and rectified before the slab pour.  This is how it looks like now after the slab was poured.


(Couldn't take a proper photo because it was hailing.)

No comments:

Post a Comment

Frame Stage

Immediately after the slab was poured, we've moved to the Frame Stage.  Frame for the ground floor is up!  How exciting to see that it&#...